Urgensi Penguatan Kedudukan Dispute Board guna Menjamin Kepastian Hukum Proyek Jalan Multi-Tahun

Paksi Aan Syuryadi(1), Muhtadi Muhtadi(2), Kasmawati Kasmawati(3),


(1) Universitas Lampung
(2) Universitas Lampung
(3) Universitas Lampung

Abstract


Multi-year infrastructure projects are inherently characterized by high legal and financial complexities, where conventional litigation and post-project arbitration often prove to be protracted, reactive, and deleterious to project continuity. While the Indonesian regulatory framework, specifically Government Regulation No. 22 of 2020, has formally recognized the Dispute Board (DB) mechanism, its practical efficacy remains constrained by a profound normative lacuna regarding executorial enforceability. This research employs a legal-doctrinal method with a comparative approach, analyzing the Indonesian landscape against the FIDIC international standards and the Statutory Adjudication models of the United Kingdom and Singapore. The findings elucidate a critical "legal gap" where DB decisions, despite being contractually binding, lack public executorial authority (executorial title). This institutional weakness incentivizes moral hazard, allowing non-compliant parties to evade immediate financial obligations through judicial delays. Consequently, this study proposes a regulatory reconstruction by integrating the principle of temporary finality into the national legislative framework, specifically through the amendment of the Construction Services Law or the Arbitration Law. The proposed model advocates for a "fast-track enforcement" mechanism within the District Courts, predicated on a limited judicial review that precludes the re-examination of technical merits. Such a reform is imperative to safeguard project liquidity (cash flow), ensure legal certainty (rechtszekerheid), and fortify the resilience of National Strategic Projects against systemic disruption.

Keywords


Dispute Board; Legal Certainty; Multi-Year Projects; Statutory Adjudication; Executorial Enforceability; Temporary Finality.

Full Text:

PDF

References


Arief, E., & Hardjomuljadi, S. (2025). Kepastian Hukum Penyelesaian Sengketa Kontrak Konstruksi Melalui Arbitrase. 5(4), 3031–3049.

Author, T., Law, C., Access, O., & Attribution, C. C. (2022). AN INTERNATIONAL CONVENTION ON EXPERT DETERMINATION AND DISPUTE BOARDS. 71(September 2020), 697–726. https://doi.org/10.1017/S0020589322000185

Bates, A., Torres-fowler, R. Z., & Llp, P. H. (2019). Dispute Boards : A Different Approach to Dispute Resolution. 198(August).

Bidang, D., Dan, H., Sanggah, P., Penanggung, S., Layanan, J., Sengketa, P., Teknis, P., Sengketa, P., Tahapan, P., Pada, M., Penyelesaian, L., Kontrak, S., Bidang, D., Dan, H., Sanggah, P., Penanggung, S., Layanan, J., & Sengketa, P. (2025). PETUNJUK TEKNIS PENYELESAIAN SENGKETA PADA TAHAPAN MEDIASI PADA LAYANAN PENYELESAIAN SENGKETA KONTRAK PENGADAAN BARANG/JASA PEMERINTAH. 1.

Bunni, N. G., O’Reilly, M., & Ong, C. (2015). The Enforcement of Dispute Adjudication Board Decisions: Persero and the FIDIC Standard Form of Contract. Arbitration: The International Journal of Arbitration, Mediation and Dispute Management, 367–374. http://www.kluwerlawonline.com/api/Product/CitationPDFURL?file=Journals%5CAMDM%5CAMDM2015058.pdf

Capper, P., Sergeant, M., & Wieliczko, M. (2020). THE LAW OF CONSTRUCTION DISPUTES (Philip Britton & Philip Capper (ed.); Third).

Chapman, B. P. H. J. (1996). Dispute Boards.

Chern, C., Sergeant, M., Wieliczko, M., & Chern, C. (2020). CHERN ON DISPUTE BOARDS Practice and Procedure (P. B. P. Capper (ed.); Fourth Edi). Routledge.

Christiawan, R. (2020). Kepastian hukum pelaksanaan kontrak konstruksi. 9(2), 85–94. https://doi.org/10.28946/rpt.v9i2.630

Hardjomuljadi, S., & Asce, A. M. (2020). Use of Dispute Avoidance and Adjudication Boards. 12(2), 1–21. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000431

Imam, M., & Andora, H. (2023). Position of Dispute Board in Construction Dispute Resolution in Indonesia. International Journal of Multicultural and Multireligious Understanding, 10(6), 344–353. https://doi.org/http://dx.doi.org/10.18415/ijmmu.v10i6.4796 Abstract

Lature, K. E. (2018). ANALISIS PENYELESAIAN SENGKETA KONSTRUKSI DI INDONESIA. UNPAR, 30, 211–222.

Laya, A. (2025). Aspek Hukum Perjanjian Kerja Dalam Proyek Bangunan.

Manaek, D. T., Sriwidodo, J., Sinaulan, R. L., & Mustofa, M. E. (2023). Kepastian Hukum Dalam Pelaksanaan Eksekusi Hasil Putusan Lembaga Arbitrase Nasional di Indonesia. Perfecto: Jurnal Ilmu Hukum, 01(2), 45–64. https://doi.org/https://doi.org/10.58977/ijih.v2i1.1 (2) 45-64

Omoto, T. (2024). Navigating Construction Conflicts : The Role of Dispute Boards in Achieving Efficient Resolution. ICCEPM 2024, 6106. https://doi.org/https://dx.doi.org/10.6106/ICCEPM.2024.1296

Pakpahan, A., Saragih, H. R., Wisatrioda, B., & Laia, K. (2025). The Efectiveness of Arbitration Mechanisms in The Resolution Of Construction Disputes In Indonesia : A Critical Analysis of Law No . 30 of 1999 on Arbitration And Alternative Dispute Resolution. 6(1), 803–808.

Plant, F. O. R., Electrical, F. O. R., Building, F. O. R., Works, E., By, D., & Contractor, T. H. E. (2017). Amendments to the FIDIC Conditions of Contract PLANT , AND FOR BUILDING AND DESIGNED BY THE CONTRACTOR.

Priyambodo, M. A. (2021). Mekanisme Penyelesian Sengketa Konstruksi Menurut Undang-Undang Nomor 2 Tahun 2017 Tentang Konstruksi. IBLAM Law Review, 01(03), 173–177.

Sugandi, H., & Saputro, A. (2025). Efektivitas Penyelesaian Sengketa Kontrak Konstruksi di Indonesia dalam Analisis Hukum Implementasi dan Tantangan Proyek Infrastruktur. Jurnal Pendidikan Indonesia, 6(3), 1232–1243.

Sumantri, M. F. A., Sami’an, & Hardjomuljadi, S. (2025). Concurrent Delay and Price Adjustment in Multi-Year Contracts: An Indonesian Construction Law Perspective. SIGn Jurnal Hukum, 6(2), 343–367.

Syarif, M., Ariani, I., Tukimun, Sahari, D., Sari, D. P., & Sulha. (2024). HUKUM KONTRAK KONSTRUKSI (A. I. A. A. Sila (ed.)). TOHAR MEDIA.

Waisapi, J. Y. (2023). THE ROLE OF THE CONSTRUCTION DISPUTE BOARD IN THE SETTLEMENT OF CONSTRUCTION DISPUTES. Eduvest-Journal of Universal Studies, 3(8), 1498–1505.

Wati, D. L., Sarifudin, F., Studi, P., Teknik, M., Tarumanagara, U., Studi, P., Teknik, M., Tarumanagara, U., Studi, P., Teknik, M., & Tarumanagara, U. (2024). Ketidaklengkapan kontrak dan sengketa konstruksi di indonesia. 7(2), 489–502.

Wirawan, I. W. S., & Budiartha, I. N. P. (2022). Multi-Year Contract in Indonesia : Its Validity and Conditions of Its Formation. International Journal of Criminal Justice Science, 17(1), 227–241. https://doi.org/10.5281/zenodo.4756102

Yudhantaka, L., Simamora, Y., & Anand, G. (2023). Binding Power of Dispute Board Judgment in Construction Dispute Settlement. 38(1), 159–170. https://doi.org/10.20473/ydk.v38i1.42717




DOI: https://doi.org/10.34007/jehss.v8i3.2979

Refbacks

  • There are currently no refbacks.


Copyright (c) 2026 Journal of Education, Humaniora and Social Sciences (JEHSS)

Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License.

Journal of Education, Humaniora and Social Sciences (JEHSS)

Publisher: Mahesa Research Center

Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International Public License